Parker ‘angry and frustrated’ over Dudley Metro delays
The Mayor of the West Midlands, Richard Parker, will launch a review into how tram projects are delivered, after the latest deadline for the West Midlands Metro’s Black Country extension was missed.
Services were due to start running between Wednesbury and Dudley at the end of August but last week, Transport for West Midlands admitted that a “safety-critical” issue meant the planned opening would now not take place until 2027 at the earliest.
Assuming services begin in January, the seven-mile extension will open more than three years later than originally planned.
Work on extending tram services into Brierley Hill began in 2020, with the extension originally scheduled to open by the end of 2023.
But a series of delays and cost increases led to the project being split into two phases, with the first four-mile stretch into Dudley then expected to be completed by 2024.
A series of deadlines have been missed since then, with frustrated Dudley leader, Cllr Patrick Harley, declaring “enough is enough” earlier this year.
“Transport for West Midlands and the Combined Authority need to get their act together and get this tram up and running, so Dudley’s got the connectivity and businesses have the break that they desperately need,” he told the BBC in June.
“Businesses are closing, people are losing money, people are losing jobs, and that’s just not right. And heads need to roll.”
Dudley Council had previously said it wanted to use the arrival of the Metro, which would reduce journey times into Birmingham down to 40 minutes and eventually connect the town with Brierley Hill, as a catalyst for future regeneration and economic growth.
An independent economic impact statement published ahead of a decision to go ahead with the scheme in 2018 estimated that, once opened, the extension to Brierley Hill could almost double the area’s economic output, from £14.4bn to £28.6bn.
A statement from TfW issued last week said it recognised the “frustration and disappointment” which had been caused by the continued delays to the extension, but said that safe operation of services was its first priority.
“This is a complex engineering project involving more than four miles of track, signalling, junctions and electrical systems. It is only through extensive testing of every individual system, with trams operating on the route, that some issues can be identified and resolved,” said a spokesperson.
“We are now in the final stages of the project and remain focused on delivering a safe, reliable and high-quality Metro service from day one.”
West Midlands Mayor Richard Parker, who was elected four years after the project got underway, said the delays were the result of systemic failures – adding that he intends to launch a review into the scheme to establish the root causes of the £400m project’s tardiness.
Speaking at a meeting of the West Midlands Combined Authority board on Friday, Parker said he had “inherited a system” whereby “private sector contractors seemingly operate without an effective mechanism to truly hold them to account”.
He told councillors he wanted stronger public control over costs, contractors and delivery on future Metro projects.
“I’m angry and frustrated – what has happened is unacceptable. We must properly and fully investigate the reasons for the repeated delays that have plagued this project since it started more than six years ago,” he said.
“And we must learn the lessons and address them on future projects to ensure they never happen again.
“Safety must come first. I won’t compromise on that. But we cannot keep accepting delay after delay.
“When projects suffer constant delay and overspending, we have to question the way projects are delivered; where responsibility and accountability should lie; where the incentives are to do better; and how oversight and governance can work more effectively.
“Right now, my priority is getting trams running into Dudley safely and as soon as possible. I want a credible plan; a date people can trust and clear accountability for getting it done.
“I am committed to extending our Metro network. It’s vital to the future of our region. But we’ve got to get better at building it.”
TfW says the Dudley extension is now in the final stages of testing and safety assurance, with driver training and route familiarisation due to get under way shortly.
The line is planned to open to Dudley in early 2027.